Project: 00712a007e Type of Project: Infrastructure Name of Project: Project of Widening Yunying Highway Bridge Project Content: At present, the clearance of the bridge is net 7+2x0.75 meters. Plan to widen one side of the bridge with clearance of 7+1x0.75 meters. Construction Condition: The project of Yunying Highway has been listed in the program of road construction of Xiaogan City. Yunying Highway Bridge is a extra-big one. To widen the present clearance becomes very necessary. Investment & Composition: Total investment amounts to US$ 4.34 million. Plan to introduce US$ 2 million of foreign investment. Economic Benefit Evaluation: As statistics and estimation, the investment payoff rate will be 29.43%, and the payoff term of 4 years. Project Status: The feasibility study has been prepared. The project is delivered for approval. Mode of Cooperation: Joint venture. Introduction to Sponsor: Communication Bureau of Yunmeng County Liaison: Song Yunlin |
||||